为了保证钢结构厂房工程安装的顺利进行,保证施工的质量、进度、安全目标,圆满完成本项工程的檩条安装工作,特编制该工程安装施工方案。
1.1 in order to ensure the steel structure workshop installation works
smoothly, ensure the quality, schedule and safety objectives of the
construction, the successful completion of the project of the purlin
installation work, special construction plan for the project
installation.
1.2 施工方案编制主要依据为: 《钢结构工程施工质量验收规范》(GB50205—2001)、 《钢结构工程质量检验评定标准》(GB50221—95)、
1.2 the main basis for compiling the construction plan is: "code for
acceptance of construction quality of steel structure" (GB50205 - 2001),
"steel structure engineering quality inspection and evaluation
standard" (GB50221 - 95),
1.3 钢结构屋面安装必须按施工图进行,当对施工图及在实际施工中发生疑问时,应通过技术主管或有关技术人员处理。
1.3 steel structure roof installation must be carried out according to
construction drawings, when the construction drawings and problems in
the actual construction, should be handled by technical directors or
technical personnel.
1.4 本施工方案中的有关要求如
JDG金属穿线管 不锈钢链板 隔离墩模具 检查井钢模具 流水槽模具 阶梯护坡模具 护坡砖模具 遮板模具与国家或行业标准、规范、规程有抵触时,应以前者为准。
1.4 if the relevant requirements in the construction plan are
inconsistent with the national or industry standards, specifications and
regulations, the former shall prevail.
1.5 安装负责人和项目经理应按照公司制定的各自的岗位职责各进其责,并协调好相互间的交接工作,保证工程安装顺利进行。
1.5 responsible for the installation and the project manager should be
in accordance with the company to develop their respective
responsibilities in each of their duties, and to coordinate mutual
handover work, ensure the installation works smoothly.